The project runs 8 two-week sprints from 2 Nov 2026 to 26 Feb 2027, with a holiday break from 24 Dec to 3 Jan. Code is complete on 26 Feb. The final demo is in the first or second week of March 2027; the days between 26 Feb and the demo are for rehearsals and bug fixes only.

Sprint Dates Theme Points Milestone
S1 2 Nov 2026 → 13 Nov 2026 Definition & Architecture 60 M0 Architecture freeze (13 Nov)
S2 16 Nov 2026 → 27 Nov 2026 SDK & Core Trace 67
S3 30 Nov 2026 → 11 Dec 2026 Trace Platform 59 M1 Vertical slice (11 Dec)
S4 14 Dec 2026 → 23 Dec 2026 AI Integrations & Detection base (short sprint) 35
S5 4 Jan 2027 → 15 Jan 2027 Detection 58
S6 18 Jan 2027 → 29 Jan 2027 Forensics 61 M2 MVP (29 Jan)
S7 1 Feb 2027 → 12 Feb 2027 Evidence, Review & Evaluation 74 M3 Feature freeze (12 Feb)
S8 15 Feb 2027 → 26 Feb 2027 Hardening, Report & Demo prep 79 M4 Code complete / release candidate (26 Feb)
Demo Week of 1 or 8 Mar 2027 Final demo Live demo

Points per person

Owner Role S1 S2 S3 S4 S5 S6 S7 S8 Total
T1 Tech Lead & Architect 12 7 5 2 5 6 4 10 51
T2 SDK & Ingestion 6 13 13 5 8 8 13 11 77
T3 Backend & Infrastructure 13 10 10 5 11 11 10 13 83
T4 AI Detection 6 8 5 5 10 8 8 8 58
T5 AI Forensics 7 8 5 5 8 10 13 11 67
T6 Frontend / UX 8 10 13 5 8 8 13 13 78
T7 Evaluation & Benchmarks 8 11 8 8 8 10 13 13 79

Sprint 4 is short (8 working days), so everyone carries less. Each person plans about 10–13 points per sprint until real velocity is known.

Stretch work

42 points are labelled stretch and have no sprint: KAN-107, KAN-114, KAN-115, KAN-122, KAN-123, KAN-124, KAN-125, KAN-128, KAN-130. Pull one in only when the sprint goal is safe and the team agrees.

Sprint 1

2 Nov 2026 → 13 Nov 2026 · Definition & Architecture · Milestone: M0 Architecture freeze (13 Nov)

Key Story Owner Tier Pts Due
KAN-15 Run kickoff: problem, users, MVP, non-goals, roles T1 MVP 2 13 Nov 2026
KAN-16 Set up Jira project, board, sprints and Confluence space T1 MVP 2 13 Nov 2026
KAN-17 Write and approve ADR-001 to ADR-004 T1 MVP 5 13 Nov 2026
KAN-18 Freeze trace/span/link contract and success-metric targets (M0) T1 MVP 3 13 Nov 2026
KAN-19 Prototype SDK API shape including inputs_from links T2 MVP 3 13 Nov 2026
KAN-20 Map span model to OpenTelemetry attributes T2 MVP 3 13 Nov 2026
KAN-21 Create repository, branch protection, PR and issue templates T3 MVP 2 13 Nov 2026
KAN-22 Docker Compose stack with PostgreSQL, Redis and MinIO T3 MVP 3 13 Nov 2026
KAN-23 FastAPI skeleton with config, /health and /ready T3 MVP 3 13 Nov 2026
KAN-24 CI pipeline: Ruff, mypy, pytest, frontend lint/type/test T3 MVP 3 13 Nov 2026
KAN-25 Write ADR-005 (Celery) and ADR-006 (capture, retention, privacy) T3 MVP 2 13 Nov 2026
KAN-26 Implement taxonomy module v1 with definitions T4 MVP 3 13 Nov 2026
KAN-27 Investigate Jev access and DecisionGate options T4 Target 3 13 Nov 2026
KAN-28 Write RCA algorithm design with hand-built fixture traces T5 MVP 5 13 Nov 2026
KAN-29 Design evidence and claim data model T5 MVP 2 13 Nov 2026
KAN-30 Scaffold Next.js console with Tailwind, ESLint, Prettier, Vitest T6 MVP 3 13 Nov 2026
KAN-31 Wireframe Traces explorer and Failures investigation screens T6 MVP 5 13 Nov 2026
KAN-32 Design benchmark suite and document benchmark T7 MVP 3 13 Nov 2026
KAN-33 Draft evaluation protocol: metrics, dev/held-out split T7 MVP 3 13 Nov 2026
KAN-34 Implement InjectedFault schema T7 MVP 2 13 Nov 2026

Sprint 2

16 Nov 2026 → 27 Nov 2026 · SDK & Core Trace

Key Story Owner Tier Pts Due
KAN-35 Publish OpenAPI contract v1 with mock server T1 MVP 5 27 Nov 2026
KAN-36 Run sprint 1 integration review T1 MVP 2 27 Nov 2026
KAN-37 SDK core: Forensics client, @trace decorator, span context manager T2 MVP 5 27 Nov 2026
KAN-38 SDK batching exporter with retry and background flush T2 MVP 3 27 Nov 2026
KAN-39 POST /v1/ingest/batch: idempotent upsert of traces, spans and links T2 MVP 5 27 Nov 2026
KAN-40 Database models and first migration: Project, ApiKey, Trace, Span, SpanLink T3 MVP 5 27 Nov 2026
KAN-41 Project and API key endpoints with hashed keys T3 MVP 5 27 Nov 2026
KAN-42 Rule validator framework and QualitySignal interface T4 MVP 5 27 Nov 2026
KAN-43 Rules: JSON schema validity and tool error T4 MVP 3 27 Nov 2026
KAN-44 Build data-flow graph from span links with parent/order fallback T5 MVP 5 27 Nov 2026
KAN-45 Encode RCA fixture traces as automated tests T5 MVP 3 27 Nov 2026
KAN-46 Console shell: navigation, session stub, typed API client from OpenAPI T6 MVP 5 27 Nov 2026
KAN-47 Trace list page with filters against mock API T6 MVP 5 27 Nov 2026
KAN-48 Document benchmark app (A) instrumented with the SDK T7 MVP 8 27 Nov 2026
KAN-49 Document benchmark faults: hallucinated entity, omitted amount, schema violation T7 MVP 3 27 Nov 2026

Sprint 3

30 Nov 2026 → 11 Dec 2026 · Trace Platform · Milestone: M1 Vertical slice (11 Dec)

Key Story Owner Tier Pts Due
KAN-50 Vertical slice integration and M1 demo (11 Dec) T1 MVP 3 11 Dec 2026
KAN-51 Generate TypeScript types from OpenAPI in CI and fail on drift T1 MVP 2 11 Dec 2026
KAN-52 Trace assembly on completion: derived totals, structure validation T2 MVP 5 11 Dec 2026
KAN-53 SDK-side redaction of secrets and configured PII patterns T2 MVP 3 11 Dec 2026
KAN-54 OpenAI adapter with automatic LLM spans T2 Target 5 11 Dec 2026
KAN-55 Store large payloads in object storage by reference T3 MVP 3 11 Dec 2026
KAN-56 Trace query API: list, filter, detail with spans and links T3 MVP 5 11 Dec 2026
KAN-57 Seed script for demo project and sample traces T3 MVP 2 11 Dec 2026
KAN-58 Rules: extracted value appears in source, citation exists T4 MVP 5 11 Dec 2026
KAN-59 RCA v0: backward walk to earliest operational error T5 MVP 5 11 Dec 2026
KAN-60 Trace explorer DAG with React Flow T6 MVP 8 11 Dec 2026
KAN-61 Timeline view and span detail drawer T6 MVP 5 11 Dec 2026
KAN-62 RAG benchmark app (B) v1 instrumented T7 MVP 8 11 Dec 2026

Sprint 4

14 Dec 2026 → 23 Dec 2026 · AI Integrations & Detection base (short sprint)

Key Story Owner Tier Pts Due
KAN-63 Publish architecture overview and ADR index in Confluence T1 MVP 2 23 Dec 2026
KAN-64 Token and cost calculation with pricing table T2 MVP 3 23 Dec 2026
KAN-65 Version metadata: pipeline, prompt, component, git commit T2 MVP 2 23 Dec 2026
KAN-66 Celery worker, AnalysisJob model and GET /v1/jobs/{id} T3 MVP 5 23 Dec 2026
KAN-67 Detection pipeline runs on trace completion T4 MVP 5 23 Dec 2026
KAN-68 Evidence store: create EvidenceRef from spans, documents and signals T5 MVP 5 23 Dec 2026
KAN-69 Settings: project and API key management UI T6 MVP 3 23 Dec 2026
KAN-70 Span payload viewer for object-store payloads T6 MVP 2 23 Dec 2026
KAN-71 RAG faults: remove relevant doc, irrelevant docs, corrupt ranking, top-k cutoff T7 MVP 5 23 Dec 2026
KAN-72 Write ADR-007 evaluation methodology T7 MVP 3 23 Dec 2026

Sprint 5

4 Jan 2027 → 15 Jan 2027 · Detection

Key Story Owner Tier Pts Due
KAN-73 Post-holiday scope checkpoint toward M2 T1 MVP 2 15 Jan 2027
KAN-74 Design candidate ranking score with T5 T1 Target 3 15 Jan 2027
KAN-75 Helpers for retrieval and tool auto-instrumentation T2 Target 5 15 Jan 2027
KAN-76 SDK quickstart guide T2 MVP 3 15 Jan 2027
KAN-77 Flags endpoint and POST /v1/traces/{id}/analyses T3 MVP 5 15 Jan 2027
KAN-78 Rate limits and request size limits T3 MVP 3 15 Jan 2027
KAN-102 Platform metrics and correlation-id logging T3 MVP 3 15 Jan 2027
KAN-79 Statistical checks: latency, cost and token anomalies T4 Target 5 15 Jan 2027
KAN-80 LLM judge: answer faithfulness to evidence T4 MVP 5 15 Jan 2027
KAN-81 RCA v1: backward traversal using quality deltas T5 MVP 8 15 Jan 2027
KAN-82 Flag button and analysis progress UI T6 MVP 3 15 Jan 2027
KAN-83 Failures list page T6 MVP 5 15 Jan 2027
KAN-84 Agent benchmark app (C) v1 with planner and tools T7 Target 8 15 Jan 2027

Sprint 6

18 Jan 2027 → 29 Jan 2027 · Forensics · Milestone: M2 MVP (29 Jan)

Key Story Owner Tier Pts Due
KAN-85 MVP end-to-end test and M2 demo (29 Jan) T1 MVP 3 29 Jan 2027
KAN-86 Implement candidate ranking v1 with T5 T1 Target 3 29 Jan 2027
KAN-87 SDK automatic linking by output object identity T2 Target 5 29 Jan 2027
KAN-88 SDK/backend contract tests T2 MVP 3 29 Jan 2027
KAN-89 Diagnosis and claim models with list/detail APIs T3 MVP 5 29 Jan 2027
KAN-90 Audit log for key/config changes and overrides T3 Target 3 29 Jan 2027
KAN-101 Datasets API (list/create, add cases) T3 MVP 3 29 Jan 2027
KAN-91 DecisionGate interface and LLM classifier fallback backend T4 Target 8 29 Jan 2027
KAN-92 Propagation labelling and span roles T5 Target 5 29 Jan 2027
KAN-93 Explanation model: evidence-cited, injection-safe diagnosis text T5 MVP 5 29 Jan 2027
KAN-94 Failure investigation page T6 MVP 8 29 Jan 2027
KAN-95 Agent faults: wrong tool, malformed args, tool timeout, loop T7 Target 5 29 Jan 2027
KAN-96 Accuracy harness on dev set: Top-1, Top-3, macro-F1 T7 MVP 5 29 Jan 2027

Sprint 7

1 Feb 2027 → 12 Feb 2027 · Evidence, Review & Evaluation · Milestone: M3 Feature freeze (12 Feb)

Key Story Owner Tier Pts Due
KAN-97 Security review checkpoint T1 MVP 2 12 Feb 2027
KAN-109 Feature freeze review and cut list (M3, 12 Feb) T1 Target 2 12 Feb 2027
KAN-98 Trace compare backend: alignment and first divergence T2 Target 5 12 Feb 2027
KAN-99 Server-side redaction safety net at ingestion T2 MVP 3 12 Feb 2027
KAN-111 Analytics queries: failures by category, step, model, prompt T2 Target 5 12 Feb 2027
KAN-100 Human feedback endpoint and eval case from confirmed diagnosis T3 MVP 5 12 Feb 2027
KAN-113 Shared staging deployment with Caddy and auto-deploy T3 Target 5 12 Feb 2027
KAN-103 Jev DecisionGate backend (if ADR-004 confirmed) with comparison logging T4 Target 5 12 Feb 2027
KAN-104 Evidence sufficiency and human review gate decisions T4 Target 3 12 Feb 2027
KAN-105 Grounding gate T5 MVP 8 12 Feb 2027
KAN-116 Candidate ranking v2 with rationale T5 Target 5 12 Feb 2027
KAN-106 Human feedback UI: confirm, correct, unsure T6 MVP 5 12 Feb 2027
KAN-118 Evaluations UI: datasets, cases, run history T6 Target 8 12 Feb 2027
KAN-108 Remaining faults for A/B/C and held-out split T7 MVP 5 12 Feb 2027
KAN-119 Regression runner with baseline comparison T7 Target 8 12 Feb 2027

Sprint 8

15 Feb 2027 → 26 Feb 2027 · Hardening, Report & Demo prep · Milestone: M4 Code complete / release candidate (26 Feb)

Key Story Owner Tier Pts Due
KAN-120 Code freeze gate (M4, 26 Feb) T1 Target 2 26 Feb 2027
KAN-121 Draft final demo script T1 Target 3 26 Feb 2027
KAN-132 Final demo rehearsals, release notes and live demo (early March) T1 MVP 5 5 Mar 2027
KAN-110 Compare screen UI with T6 T2 Target 5 26 Feb 2027
KAN-133 SDK guide and API reference polish T2 MVP 3 26 Feb 2027
KAN-134 Bug fixing: SDK, ingestion, compare, analytics T2 MVP 3 26 Feb 2027
KAN-112 Capture policy enforcement and retention job T3 MVP 5 26 Feb 2027
KAN-135 Security tests: redaction, cross-project, oversized, prompt injection T3 MVP 5 26 Feb 2027
KAN-136 Release candidate on staging with runbook (M4, 26 Feb) T3 MVP 3 26 Feb 2027
KAN-126 Benchmark DecisionGate backends vs rules vs LLM judge T4 Target 5 26 Feb 2027
KAN-137 Detection documentation and bug fixes T4 MVP 3 26 Feb 2027
KAN-117 Tune RCA on dev set T5 MVP 3 26 Feb 2027
KAN-127 Support held-out evaluation and fix RCA defects T5 MVP 5 26 Feb 2027
KAN-138 Forensics documentation and bug fixes T5 MVP 3 26 Feb 2027
KAN-129 Overview and Analytics dashboards T6 Target 8 26 Feb 2027
KAN-139 Playwright E2E for main flow and UI polish T6 MVP 5 26 Feb 2027
KAN-131 Held-out accuracy runs for final metrics T7 MVP 5 26 Feb 2027
KAN-140 Final evaluation report T7 MVP 8 26 Feb 2027